State agencies cannot treat tree plantation as a mere paperwork formality while rapidly clearing green cover for urban infrastructure, the Bombay High Court observed on Wednesday [MMRDA v. Union of India]
A Bench of Chief Justice Mahesh C Tripathi and Justice Advait Sethna stressed that authorities must undertake afforestation in advance rather than seeking court permissions first and leaving ecological restoration for later.
These oral remarks came while hearing a plea filed by the Mumbai Metropolitan Region Development Authority (MMRDA), a State urban planning agency, seeking leave to divert 0.2869 hectares of mangrove forest land. Such approval was sought to build an 8.85-km elevated Automated Rapid Transit System (ARTS), a driverless ‘electric pod car’ network, in Mumbai’s Bandra-Kurla Complex business district.
The plea was filed as per a 2018 High Court ruling aimed at protecting Maharashtra's coastal wetlands. The judgment mandates that no development affecting mangroves can proceed without explicit permission from the Court in the larger public interest.
Although no mangroves will be felled, six trees are affected by the alignment, and the MMRDA has undertaken to plant 100 trees as compensation.
During the proceedings, advocate Saket Mone for MMRDA argued that the elevated corridor is vital for last-mile connectivity. He added that tree plantation fell under the Forest Department's domain rather than the construction expert body.
The Bench questioned why compensatory measures had not been initiated the moment the project had been conceptualised.
“Greenery should be maintained. It will take some time for trees to grow. Once this project is coined by the authority, why are efforts to maintain the ecosystem not taken by authorities in advance, instead of putting stringent conditions for later? Why not show in advance the bonafide genuine effort?" the Court asked.
It pointed to the gap between regulatory filings and ground reality.
“If 30% cover is required, then how can we accord permission? Everything is on paper. But effectively nothing has happened for planting trees."
Maharashtra Advocate General Milind Sathe explained that a shortage of suitable saline land delays mangrove plantation. He also explained that saplings are planted pre-monsoon to ensure survival.
The Court asked the State to submit concrete data from the past five years showing total green cover, losses, and sapling survival rates before passing orders.
“We are not against the project. However, we do not want to move till compliance is seen," the Bench stated.
It posted the matter to November 30.
Mone was briefed by advocate Fatema Ansari for MMRDA.
Sathe was briefed by additional government pleader Onkar Chandurkar.