Here's is why CJI Surya Kant recused from Supertech insolvency case

The proceedings concern the completion of stalled Supertech housing projects and protection of homebuyers' interests.

Debayan Roy

Chief Justice of India (CJI) Surya Kant on Monday recused himself from hearing a Supertech insolvency and homebuyers' dispute before the Supreme Court after noting that one of the litigants was personally known to him [Apex Heights Pvt. Ltd. v Ram Kishor Arora & Anr.].

The matter was being heard by a Bench of CJI Surya Kant, Justice Joymalya Bagchi and Justice V Mohana.

During todays hearing, CJI Kant noted a special Bench would be constituted to hear the matter.

“One of the applicants was incidentally known to me. I will have to constitute a special bench... remotely known to me, not my client or my relative, but known to me. Somebody should have been conscious of this fact. Why unnecessarily become a party?” he remarked.

CJI Surya Kant, Justice Joymalya Bagchi, Justice V Mohana

The proceedings concern the completion of stalled housing projects of real estate developer Supertech Limited and the protection of homebuyers who have been waiting for possession of their homes for years.

The case arose from insolvency proceedings initiated against Supertech by Union Bank of India. The National Company Law Tribunal (NCLT) admitted the bank's insolvency application against the developer on March 25, 2022. The subsequent proceedings before the National Company Law Appellate Tribunal (NCLAT) led to directions for the completion of 16 stalled projects through State-owned NBCC India Limited.

In February this year, the Supreme Court upheld the NCLAT's decision to involve NBCC in completing 16 stalled Supertech projects, prioritising the interests of homebuyers who had been waiting for more than two decades.

The Court said homebuyers' interests in securing their homes would take precedence, for the time being, over competing claims of secured creditors, operational creditors and land authorities. It also directed that existing allottees should not face cost escalation beyond what was provided for in their builder-buyer agreements.

The Supreme Court's directions also provided for oversight through an Apex Court Committee and project-level committees to monitor construction and fund management.

The matter has since continued before the Supreme Court, with applications and requests for directions concerning the implementation of the project-completion framework. On November 16, the Court granted parties time until November 20 to submit their suggestions to the amicus curiae, who was to place them before the Court in a collated format.

[Read Live Coverage]

Rohit Bhansali joins Starbucks India as Head - Legal, Permits and Licensing

Supreme Court upholds quashing of IT Department's proceedings against defunct Reliance companies

Shardul Amarchand Mangaldas advises IFC on $150 million financing to SBI GIFT City

Khaitan & Co advises Blackstone on ₹5,000 crore equity investment in IIFL Finance

Universal Legal acts for DSP Designs on its sale to Anarock Group

SCROLL FOR NEXT