Pallavi Bedi, Ashita Bali 
Leading Questions

Renewable energy in India: From capacity expansion to energy transition

Pallavi Bedi and Ashita Bali discuss how India’s renewable-energy sector is rapidly expanding, supported by ambitious climate targets and policies, while facing challenges in certain areas.

Pallavi Bedi, Ashita Bali

In this Leading Questions piece, Pallavi Bedi and Ashita Bali discuss how India’s renewable-energy sector is rapidly expanding, supported by ambitious climate targets and policies, while facing challenges in project delivery, regulation, and grid integration.

Question: Please provide a general overview of India's renewable energy sector and the policy initiatives driving its growth.

Answer: India's installed renewable energy capacity (which encompasses solar, wind, hydro, biomass and nuclear power) stood at 312.24 giga-watt ("GW") as of November 12, 2026, constituting 55% of India's total installed capacity (i.e., approximately 564 GW). Over the past decade, India's renewable energy sector has witnessed significant growth – the solar installed capacity increased from 2.6 GW in 2014 to around 174.5 GW at present, and the wind installed capacity increased from 21 GW in 2014 to around 59.5 GW at present.

India has ambitious targets to achieve 500 GW of installed capacity from non-fossil sources by 2030, and honour its commitments under the Paris Agreement on climate change. Notably, when India ratified the Paris Agreement on October 2, 2016, it had committed to reduce its emission intensity to 35% below 2005 levels by 2030 and ensure that about 40% cumulative power capacity is sourced from non-fossil fuel-based energy resources by 2030. Subsequently, in August, 2022, India enhanced its commitment to reduce emission intensity to 45% below 2005 levels by 2030 and achieve about 50% of its power from non-fossil fuel-based energy resources by 2030. More recently, in March 2026, India further enhanced its target to reduce emission intensity to 47% below 2005 levels by 2035.

These figures underscore the Government of India's commitment to accelerate the country's clean energy transition and position India as a global leader in renewable energy.

While the initial growth was fueled by feed-in tariff, renewable purchase obligations, clean development mechanism benefits, tax breaks etc., some of the recent key policy initiatives driving the growth of this sector include:

  • renewable consumption obligation;

  • grid integration and development of transmission network and grid connectivity arrangements;

  • increasing emphasis on battery energy storage systems ("BESS") to address the intermittent nature of renewable energy;

  • inter-State transmission charges waiver for eligible renewable energy projects (albeit, this waiver is progressively being phased out); and

  • promotion of domestic manufacturing and supply-chain development through production linked incentive schemes and introduction of domestic sourcing requirements (including under the Approved List of Models and Manufacturers).

Question: What are the key contractual provisions that are typically negotiated in agreements for the development of a renewable energy project?

Answer: The contractual framework for a renewable energy project typically encompasses a range of agreements, including engineering, procurement and construction ("EPC") contracts, operation and maintenance ("O&M") contracts, inter-connection agreements, power purchase agreements and financing agreements.

At the development stage, the EPC contract is the principal agreement governing the engineering, procurement, construction and commissioning aspects of the project. Some of the key provisions typically negotiated under an EPC contract include:

  • Contract structure: Whether the EPC contract would be structured as a split contract (comprising of supply contract, works contract, services contract and a wrap agreement) or as a turnkey contract – this merits consideration specifically from a tax perspective.

  • Project timelines and delays: The construction milestones and commissioning timelines, delays and the consequences of such delays (including liquidated damages);

  • Scope of work and variations: The scope of work, procedure for variation to the scope of work and the allocation of the cost of additional works;

  • Performance standards: Technical and operational performance parameters, testing and handover criteria and remedies for failure to meet the agreed performance standards;

  • Warranties and defect liability: The extent and duration of warranties, defect liability period and the contractor's obligation to rectify defects;

  • Force majeure: The events qualifying as a force majeure event, the relief and consequences of prolonged force majeure events;

  • Change in law: The events qualifying as a change in law event, allocation of risks arising from change in laws and the associated relief (including a cost adjustment or extension of time); and

  • Payment security mechanism.

Relevantly, the provisions of the EPC contract must be aligned with the corresponding provisions of the other project agreements, particularly the O&M contract and power purchase agreement, as delays or defaults in one agreement may affect the developer's or owner's ability to perform their respective obligations under the other agreements. For instance, commissioning timelines, events constituting force majeure and change in law and the associated relief should be appropriately aligned across these agreements to ensure that the relevant risks are adequately passed through to the party best placed to manage or bear them.

Question: What are the key legal and regulatory concerns in connection with the development of renewable energy projects in India?

Answer: While the government of India has introduced several measures and initiatives to support the growth of renewable energy sector, some of the key legal and regulatory concerns that the industry continues to grapple with include:

  • delays in the development of the transmission infrastructure;

  • availability of banking facilities;

  • commercial viability and cost implications of domestic sourcing requirements;

  • phased withdrawal of waiver of inter-State transmission charges;

  • land acquisition, more so in projects involving forest land or land in protected areas;

  • delays in obtaining project approvals and registrations;

  • availability and structuring of financing arrangements;

  • delays in execution of the power purchase agreement following the award of a project;

  • end of life management of renewable energy assets.

Question: What has been the most preferred arrangement for commercial and industrial consumers to procure renewable energy in the recent times, and what are the factors driving this preference?

Answer: Procurement of renewable energy through open access and captive and group captive arrangements has generated significant interest among commercial and industrial ("C&I") consumers, who are increasingly looking to optimise electricity costs and meet their sustainability targets.

The notification of Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022 ("Green Energy OA Rules") has helped facilitate access to affordable, reliable and sustainable green energy, through open access, to all consumers who have a contracted demand or sanctioned load of at least 100 kilowatts, whether through a single connection or through multiple connections aggregating to at least 100 kilowatts located in the same electricity division of a distribution licensee. Notably, there are no load restrictions for captive consumers. Pursuant to the Green Energy OA Rules: (i) the cross-subsidy surcharge for green energy open access consumer is capped at 50% of the surcharge determined for the year in which the open access is granted, with such cap remaining applicable for 12 years from commissioning, and (ii) additional surcharge would not be applicable for electricity generated from offshore wind projects which are commissioned by December, 2032 and supplied to open access consumers.

Further, captive power plant arrangements have gained traction, owing inter alia to the incentivisation of this structure, including the waiver of cross-subsidy surcharge and additional surcharge on the power consumed for captive use. To qualify for this waiver, the captive user must hold at least 26% ownership in the power plant, and consume at least 51% of the aggregate electricity generated by such power plant, determined on an annual basis. The Electricity (Amendment) Rules, 2026 amending the Electricity Rules, 2005 have brought greater clarity to the ownership and consumption requirements and the treatment of group companies and special purpose vehicles.

Question: What role are hybrid renewable energy projects and battery energy storage systems expected to play in India's energy transition?

Answer: Recent developments in the renewable energy space (including the transition to hybrid power projects (solar and wind projects) and growing emphasis on integrating BESS) are geared towards addressing the intermittent nature of renewable energy projects and moving beyond the development of standalone solar and wind power projects. These developments are particularly significant as India seeks to inch closer to its target of achieving 500 GW of installed capacity from non-fossil sources by 2030 and reduce its emission intensity to 47% below 2005 levels by 2035.

The government of India has undertaken a slew of measures to accelerate the deployment of BESS, including the issuance, by the Ministry of Power, inter alia, of the:

(i) guidelines to promote the development of pumped storage projects in April, 2023,

(ii) National Framework for Promoting Energy Storage Systems in August, 2023,

(iii) viability gap funding scheme for development of BESS in March, 2024,

(iv) advisory on co-locating energy storage systems with solar power projects to enhance grid stability and cost efficiency in February, 2025, and

(v) viability gap funding scheme for development of BESS supported through power system development fund in June, 2025.

Further, the inter-State transmission charges have been waived for: (i) hydro pumped storage projects for which the construction work is awarded on or before June 30, 2028, for a period of 25 years, and (ii) BESS commissioned on or before June 30, 2028, where such storage system is connected at a sub-station where a renewable energy generating system ("REGS") is connected and is charged from such REGS, for a period of 12 years.

For developers and C&I consumers, hybrid renewable energy projects and BESS offer the ability to maintain uninterrupted power supply and reduce dependence on conventional sources of electricity. As the storage technologies mature and the regulatory framework evolves further, hybrid projects and BESS are expected to play a critical role in India's energy transition.

Pallavi Bedi is a Partner and Ashita Bali is an Associate Partner at Phoenix Legal.

Private universities audit case in Supreme Court shifted from Justice Ahsanuddin Amanullah Bench

Calcutta High Court initiates contempt of court case against Abhishek Banerjee for remarks against judges

Delhi High Court pulls up Arvind Kejriwal, AAP leaders for failing to reply to contempt of court case

Supreme Court upholds stay on conviction of Azam Khan in forged birth certificate case; extends same relief to wife, son

Actress assault: Kerala High Court dismisses plea by survivor's lawyer for contempt action against trial judge Honey Varghese

SCROLL FOR NEXT